GBA CASE HISTORY # 58
| Description |
|
Member-Firm develops plans for construction of landfill cells, for a private waste disposal company. When the project manager of client insists on the changes of design and when the member-firm's suggestions do not get documented, the member-firm gets the blame.
claim resolution, landfill expansion, groundwater pumps, client retention, innovation risks, negotiated claim , construction-materials engineering and testing ,landfill-cell failure, limitation of liability,
|
|