GBA CASE HISTORY # 43

Item Options
Sign in for your pricing!
Price: $350.00
Quantity: *
 
Description
Member-Firm conducts feasibility study, then reviews dewatering designs for a five-story underground garage near the ocean. The constructor in charge of dewatering did not follow the instructions of the project engineer regarding the dewatering designs, the number of wells required and installation of meters, which caused delays and firing of constructor in charge and other lingering disputes between the parties.
 


CoMET, construction-claims attorney,  constructors, dewatering, documentation, favors, geotechnical engineering, go/no-go analysis,oral agreement, professional-liability insurance, sealing others' plans, public agency